Construction Act Ontario: Trust Rules and Personal Liability

Listen Anywhere

A $48,000 draw lands on Monday. By Friday it has covered payroll for crews on two other jobs and the truck lease. The supplier on the job that draw came from gets told “next week.”

Most contractors would call that a normal week. Under Ontario’s Construction Act, it can be a breach of trust, and the owners of the company can end up paying for it personally.

On this episode of The Deconstruction Podcast, Kosta and Johny went through an Ottawa court case where that happened, and what a small contractor can do about it.

 

What the Ontario Construction Act says about the money you get paid

Part of the Act deals with trust funds. In plain terms, when you’re paid for a job, the money owed to the subs and suppliers on that job is held in trust for them. You can’t put it toward other jobs or your own overhead until the people under you on that job are paid.

The rule runs down the chain. A GC holds money in trust for its trades, and a subtrade holds it for its own suppliers.

A second section makes it personal. Directors and officers who go along with a breach of trust can be held liable themselves, even when the company is incorporated.

Johny deals with draws and payment disputes every month and still didn’t know this was written into the Act. His instinct already matched it, though. He has a saying he’s strict about: you don’t take from Peter to pay Paul.

 

The Ottawa case: two owners personally liable for a supplier bill

The case is Morin Bros. Building Supplies v. Bond Group Ottawa 2018 (2025 ONSC 5561), decided in Ontario Superior Court.

A contractor bought materials on credit for a few Ottawa projects. The owners of those projects paid the contractor. The supplier was never paid in full, and it sued for the unpaid invoices and for breach of trust.

The contractor said it kept a ledger for each project. All of the money still went into one general chequing account, the same account it used to pay trades, suppliers, business expenses and overhead. When it had to show where the project money went, it couldn’t produce the records.

The judge found a breach of trust and held both directors personally liable for it. The credit agreement signed years earlier came with a personal guarantee and interest of 25.5% a year, compounded monthly, and the court applied that rate to what was owed.

Nobody had to prove the owners pocketed anything. Going along with how the money was handled was enough.

 

How a normal week becomes a breach of trust

Kosta built an example on the show to make it concrete. Dave is an electrician with six people and one chequing account.

On Monday the GC pays him a $48,000 progress draw for a job on Maple Street. Out of that draw, Dave owes $16,000 to his supplier, $6,000 to a trenching sub and $9,000 in wages for the crew on that job. That’s $31,000 that belongs to people who worked on or supplied Maple Street. The other $17,000 is Dave’s overhead and profit.

The same week, Dave has $14,000 in payroll for crews on two other jobs and an $1,800 truck payment. It all comes out of the same account. He tells the Maple Street supplier he’ll pay next week, when another GC pays him.

That GC pays late. Next week turns into next month. The supplier’s lawyer sends a demand letter, then sues the company for the invoices and Dave personally for breach of trust.

Dave never took a dollar for himself. He paid his guys and kept another job moving. Under the Act, the Maple Street money was still spent on something other than Maple Street.

 

“It’s not your money”

Kosta asked Johny whether Dave is the bad guy. Johny wouldn’t call him right or wrong. Dave was doing what he had to do to keep the company going, and if he’s short, it’s probably because someone isn’t paying him either.

Johny was also honest that most companies move money between jobs at some point. His rule is about timing. If you use Peter’s money today, Peter gets paid by the end of the week or early the next one, and you’d better know which receivable is going to cover it.

His sympathy ends with the contractor who gets paid and spends it on himself. Years ago a builder owed him hundreds of thousands of dollars. The builder showed up late to a meeting full of lawyers in a chauffeured Rolls-Royce Phantom and a $5,000 suit. Johny’s reaction then is what the Act says now. It’s not your money. You got paid, so pay.

His longer-term answer is a bankroll. Treat the company as its own employee. Every job has to cover your pay and overhead, with money left over that stays in the company. That reserve is what lets you float a slow month without reaching into another job’s draw.

 

Do contractors need a separate bank account for every job?

On the show, the idea of opening a bank account for every project got the reaction you’d expect. Johny called it ridiculous for a small company.

The Act asks for less than that. It says trust money has to go into a bank account in your name, with written records of what came in and what was paid out. Money from several jobs can sit in the same account as long as you keep those records separately for each job.

The unsettled part is whether that account can be your everyday operating account. In a 2023 Ontario decision, a contractor that kept trust money in its general account, tracked project by project, was found not to have breached the trust. In the Ottawa case, the judge treated the lack of a separate trust account as a breach. Construction lawyers at WeirFoulds and Gowling WLG, writing about the decision, land on the same practical answer: one trust account kept apart from your operating account, with records for each job.

That’s a conversation for your lawyer and your accountant. This post is general information and isn’t legal advice.

 

Job costing is the record that protects you

Whatever the courts settle on for bank accounts, both decisions turned on records. The contractor who could show where each job’s money went was fine. The one who couldn’t lost.

That is what job costing gives you. For every job, you know what came in and where it went.

Johny cares about it for a practical reason. When you’re on site and something comes up, you want to know where you stand on that job right then, without waiting until you get home or calling your bookkeeper. If you allowed $1,000 for materials, you’ve spent $1,200 and you still need $800 more to finish, you want to see that today.

It applies whether you’re one person in a truck or running a hundred employees.

Jobtable is built around the job for this reason. Receipts and approved timesheets post to the job they belong to, so each job shows its own costs and profit, and the accounts receivable report shows who owes you and for how long.

👉 Learn more at https://www.jobtable.com

 

If you’re the one waiting to get paid

The trust rules work in your favour too. If the GC was paid for your work and didn’t pay you, that money was supposed to be held in trust for you. That can give you a claim beyond your lien, including against the GC’s directors personally.

It has limits. Johny pointed out that the money sometimes stops above the GC. When a developer’s financing dries up and a project goes into receivership, the bank gets paid first, and trades can wait years for whatever is left.

Subtrades almost never ask a GC whether their money is being held in trust, and Johny said he never has. What he does is stay on his receivables. One of his favourite clients, a man in his eighties, tells him the same thing every time they talk: stay on top of your receivables, friends or no friends.

So when someone says they’ll pay by Friday and Friday passes, Johny follows up on Monday and keeps following up every day after that. It keeps the pressure on, and it leaves a written trail if the file ever goes to a lawyer.

 

FAQ

 

Do I need a separate trust account under the Ontario Construction Act?

The Act requires trust money to be deposited in a bank account in your name, with written records for each trust. It doesn’t use the words “separate trust account,” and Ontario judges have read it differently. After the 2025 Ottawa decision, the cautious approach is a trust account kept apart from your operating account. Ask a construction lawyer how it applies to your business.

 

Can I be personally liable if my company is incorporated?

Yes. Under the Act, directors, officers and anyone who effectively controls the company can be personally liable if they go along with conduct they knew, or should have known, was a breach of trust. A supplier doesn’t have to show that you took money for yourself.

 

Can I use money from one job to cover costs on another?

Only after the subs and suppliers on the first job have been paid what they’re owed for it. Until then, that part of the money is held in trust for them.

 

Does this apply to subcontractors or only general contractors?

Both. A subtrade that gets paid on a job holds that money in trust for its own suppliers and sub-subs on that job.

 

Does this apply outside Ontario?

The case and the rules in this post are Ontario law. Several other provinces have trust rules in their own lien legislation and the details differ, so check what applies where you work.

 

One question to ask yourself this week

Pull up the last draw you received. If a supplier’s lawyer asked tomorrow where that money went, how long would it take you to show them?

Run every job as its own job

Jobtable is built around the job, so costs, invoices and payments stay with the work they belong to. It's simple software for contractors who want to know where each job stands. Try it free for 14 days.