The homeowners paid. That’s the part of this story most contractors don’t expect.

On a $2.2 million custom home in Mississauga, the owners paid the builder well over $200,000 in extras on top of the contract price. Ten days after they moved in, the builder registered a $240,000 lien on the house for more extras he said they still owed. It took seven years to get to a judgment. When it finally came down this past summer, a judge went through every disputed extra line by line, and the builder walked away about $12,000 ahead before interest and legal bills.

Kosta and Johny broke the case down on The Deconstruction Podcast. If you do residential work and you’ve ever said “yeah, we’ll sort out the cost later” while standing in a client’s kitchen, this one is about you.

 

What happened in L.S.I. Engineering v. Morales

The case is L.S.I. Engineering Limited v. Morales, 2026 ONSC 4472, decided by the Ontario Superior Court on July 31, 2026, after an eight-day trial. The contract was signed in 2017 and the owners moved in during 2019.

Two problems sat at the centre of it. The builder was claiming money for extras that were never signed off in writing. The homeowners also found out the builder had installed a simpler heating system than the one on the approved mechanical drawings, without telling them.

The judge ruled against the builder on both. The lien fight that was supposed to recover $240,000 ended with the builder awarded about $57,000 and the homeowners awarded about $45,000 on their side of the claim.

 

Change orders in construction: why the judge wouldn’t budge

The builder’s own contract said any changes had to be approved in writing. That clause decided most of the case.

Roughly $58,000 of the disputed extras had nothing in writing behind them. That included a landing on the stairs at about $27,000, stone around the barbecue at about $4,000, work on the home gym, and a design fee. The work may well have been done. The judge still refused to award it, because no signed change order existed for any of it.

The builder argued he’d done some of that work as customer service. The court’s position was simple: if you choose to do work without the approval your contract requires, you carry the risk of not getting paid for it.

That’s a hard result, and it’s worth thinking about who actually pays for it. If the builder marked that work up 50%, something like half of that $58,000 was money he likely owed to subtrades and suppliers. He paid them. He never got it back.

 

Why extras pile up on custom builds

Nobody on the show was surprised by the size of the extras. Johny’s point was that 10 to 15% over contract is normal on a custom home. Commercial and industrial lenders build a contingency of 10 to 20% into budgets for the same reason.

Drawings look settled on paper. Then the walls go up, and the owner walks the space and wants a wall gone. That means a beam, and the beam means a price. They want marble instead of porcelain. They decide halfway through that they do want the heated driveway after all, and that’s $40,000 on its own. Every one of those decisions happens while the job is already behind schedule, which on a construction project is from about the day the first bucket goes in the ground.

The extras are expected. What causes the trouble is how fast they get agreed to.

 

Why contractors skip the paperwork

The honest answer is the relationship. After a year on someone’s house, you know their kids’ names. They’ve been paying their bills on time. Asking them to sign a form for a $6,000 faucet upgrade feels like telling them you don’t trust them.

Johny compared it to a friend asking to borrow $1,000 until Friday. You don’t write up a contract for that. Kosta pushed back on the comparison, and the court sided with Kosta. A $2.2 million build is a business deal, and the paperwork is what the two sides agreed would control cost and scope.

The commercial side of the industry handles this with much less emotion. Say a client wants a different faucet than the one on the drawings. The trade prices the difference, submits a quote, waits for the purchase order to be updated, and only then orders the new faucet. Nobody takes it personally because that’s simply how the work gets done.

 

A change order process you can run on site

The fix doesn’t need to slow the job down. It needs to happen in the room, while the client is still standing there.

Start by getting your terms straight. A quote is a price on work you haven’t been hired for yet. Once the client approves it, it becomes a job, and that original approval is your contract. Anything the client asks for after that is an extra. Each extra gets its own quote attached to that same job, so it stays separate from the original scope and is easy to track.

On site, that looks like this. The client asks for the change. You pull out your phone, add the line items for the extra, and turn the screen around so they can see the description and the price. Then you send it to them and ask for a signature right there. Everyone has their phone on them. The whole thing takes a couple of minutes.

Your software might not collect digital signatures. In that case, an email from the client saying “I’ve reviewed the extra and agree to the cost, please proceed” is far better than nothing. Johny has won end-of-project arguments on commercial jobs with exactly that kind of email. It came from a project manager who wanted the work to keep moving while the person who normally signs was out of the office.

Jobtable is built around this flow. You quote extras right on the existing job, the client signs off, and the approved items carry through to the invoice, so nobody is arguing about them months later.

👉 Learn more at https://www.jobtable.com

 

Getting a signature from a friend without it getting awkward

Johny’s approach with friends and family is to make the signature about accuracy. Something like: “Just put a signature on this. It adds it to the job, and my guys work off what’s on the job, so this makes sure we build exactly what you asked for.”

That’s true, too. Maybe you won’t touch that bathroom for two months. Maybe the guy who heard the request calls in sick and someone else fills in. Either way, the signed quote is the only record of what was agreed. Protecting your payment is one reason to do it. Making sure nothing gets missed is the other, and it’s the easier one to say out loud.

 

The heating swap: the other side of the same problem

The builder lost on paperwork in the other direction too.

The approved mechanical drawings called for three manifolds, six zones, and seventeen loops in the in-floor heating. What went in was two manifolds, two zones, and ten loops. Nobody signed off on the change.

The court found the drawings were part of the contract, so installing a simpler system without written approval was a material breach. Damages were assessed at a conservative $15 per square foot to reflect the gap between what was designed and what was built.

Johny was careful not to guess at the builder’s reasons. Loops get changed for real reasons on site: a beam in the way, a bulkhead the owner didn’t want, or an HVAC sub suggesting a layout that performs better. Any of those might have been a good call.

On commercial work, that change goes in writing with a spec sheet to the GC, who loops in the engineer and consultants. If it’s approved, you make the change. If you skip that step and the engineer finds it during a field review, it doesn’t matter whether your version works better. You’re replacing it on your own dime.

The same rule that would have protected the builder’s $58,000 is the one he broke on the heating system. Changes go in writing, whichever direction the money moves.

 

Tarion and the personal guarantee

The homeowners had complained to Tarion about the missing manifold. Tarion’s engineer checked that the system turned on and didn’t compare it to the drawings. The court found Tarion failed in its duty to investigate and held it jointly liable with the builder.

The builder didn’t escape that either. Tarion was granted the right to recover its share from the builder, and on the show Kosta noted the builder had signed a personal guarantee. So that money came back to the builder too.

 

What seven years in court actually paid

Put the whole thing together. A $240,000 lien turned into roughly $57,000 for the builder and $45,000 for the homeowners. That’s about $12,000 net for the builder after seven years, before interest and before what both sides spent on lawyers. Johny guessed each side spent at least $30,000.

He also raised a point the judgment doesn’t really cover. The builder fronted that money in 2019. Even at 6% on a line of credit, compounded over seven years, the cost of carrying it eats most of what he was awarded.

Compare that to a client Kosta mentioned from last week. A homeowner came back months after a job claiming something had been done wrong. The contractor had daily logs, photos, and signed quotes on every extra. The claim was dropped before a lawyer ever got involved.

 

FAQ

What is a change order in construction?

A change order is a written, signed agreement to change the original scope of a construction contract after work has started. It describes the change, states the cost or credit, and records that the client approved it before the work was done.

 

Can a contractor get paid for extras without a signed change order?

Sometimes, but then you’re relying on the court to believe your version of a conversation. In this Ontario case, the contract required written approval for changes. The judge disallowed about $58,000 in extras that had none, even though the work may have been done.

 

Does a client’s email count as approval for an extra?

An email from the client that clearly approves the specific extra and its price is much stronger than a verbal okay. A signed quote is better still. Check what your contract requires, since some contracts specify the form approval has to take.

 

Can a builder change what’s on the mechanical drawings?

Only with written approval. In this case the court treated the approved mechanical drawings as part of the contract, so installing a simpler heating system without sign-off was a material breach.

 

How long do you have to register a construction lien in Ontario?

Under Ontario’s Construction Act you generally have 60 days. The clock starts at the earlier of two dates: when the contract is completed, abandoned, or terminated, or when you last supplied services or materials. Timelines can vary by situation, so talk to a construction lawyer if a lien is on the table.

 

The signature is cheaper than the lawsuit

Johny’s line on the show was that $150 or $200 a month for software that documents your extras matters as much as the quality of your work. Seven years and a $12,000 net result makes a decent case for that.

So think about the last job you finished. If that client called tomorrow and disputed every extra you billed, how many of them could you prove they approved?