A subcontractor in Ottawa finished its work on the city’s new light rail line. Nobody said the work was bad, and nobody said the money wasn’t owed. The general contractor still went to court to keep $703,000 of it.
The money was holdback, and the whole fight was over one date. If the judge had read the calendar the other way, the sub would have lost all of it.
On episode 81 of The Deconstruction Podcast, Kosta and Johny broke down Bradley-Kelly Construction v. AtkinsRéalis, an Ontario Superior Court decision from September 2026. It’s a big infrastructure case, but the lessons apply to any contractor who has ever been paid 90% of an invoice and waited on the rest.
What is a holdback in construction?
Say you’re a sub and you send your client a $10,000 invoice. You show a 10% holdback on it, so $1,000 comes off and they pay you $9,000. When the job is done, you bill the last $1,000.
That’s how holdback looks on paper. The part a lot of contractors have backwards is who’s holding it. The $1,000 sits with your client, and it’s still your money. Ontario’s Construction Act requires every payer on a job to keep back 10% of what they owe: the owner holds back from the GC, the GC from the subs, and the subs from their own subs.
The point is to leave money on the job that unpaid trades and suppliers further down the chain can claim against with a lien. Whoever is holding the holdback holds it in trust for the people below them. If an owner pays it out too early and a sub liens the job, the owner can end up paying twice.
The timing is also longer than “the end of the job.” The payer can keep the holdback until the lien period runs out, which is 60 days after the work is done, and then has 14 days to pay. Since January 1, 2026, owners on new contracts also have to release holdback every year on the contract anniversary, which makes a real difference on jobs that run two or three years.
Holdback applies to small jobs too
There’s no minimum job size. Holdback applies to any contract on a job where someone could file a lien, so the $40,000 restaurant fit-out, the office reno and the rooftop unit swap all count. On a $40,000 job, $4,000 is supposed to stay back. Even a homeowner who hires a contractor for a kitchen renovation counts as an owner under the Act.
Johny’s experience lines up with that. On commercial work, he’s had holdback taken on jobs as small as $3,000, usually because the contract (a CCDC or CCA form) requires it. On residential, most contractors he knows have never had anyone hold back on them. The rule applies there too. Most people just don’t follow it.
He also pointed out what it costs. On a lot of jobs, the holdback is roughly where your profit sits, so you wait until the very end to see your margin. Tracking 10% across a pile of invoices of different sizes, then billing it all at the end, turns into a spreadsheet mess fast. That’s why Jobtable handles holdback on an invoice with one click.
How a sub four levels down got caught in someone else’s fight
The chain on this job was long. The City of Ottawa hired a group called TransitNext to design, build, finance and maintain the $1.6 billion Stage 2 Trillium Line extension. Under them was AtkinsRéalis (formerly SNC-Lavalin), the main construction partner. Under AtkinsRéalis was GIP Construction (formerly Aecon), the sub-GC for civil and electrical.
GIP hired Bradley-Kelly, an Ottawa company that’s been around since 1982, for roadway lighting, duct banks and utility work at two sites: the road realignment and park-and-ride at Earl Armstrong, and the Walkley Yard, where the trains are maintained.
Bradley-Kelly never had a contract with AtkinsRéalis. It was four levels down, doing its own work.
At the end of 2023, AtkinsRéalis and GIP fell out over unpaid invoices and delays. GIP stopped working, AtkinsRéalis terminated them, and the money stopped flowing down to the company at the bottom.
Johny’s take was blunt. The sub usually has no contact with the client at the top, and when two companies above it get into a fight, the sub is the one left without answers. A sub in that spot has often been paid late all along and carrying the job on a line of credit, so by the time the holdback is the only money left, it’s usually the profit on the whole contract.
Two liens, one job, and the date that almost cost $703,000
In February 2024, Bradley-Kelly filed two liens, one for each site. AtkinsRéalis settled the Walkley Yard lien and paid out $615,000 in holdback. It fought the other one, $703,000 on Earl Armstrong.
The GC’s argument was that these were two separate jobs. Bradley-Kelly finished Earl Armstrong on December 27, 2023, so the GC said the lien clock started that day and the filing came too late.
Bradley-Kelly’s answer was that this was one transit line. The trains can’t run without the road work, and they can’t run without the maintenance yard. Its last day on the job was January 25, 2024, a month later, which put the lien on time.
The judge agreed with the sub: one job, one clock, lien preserved, release the $703,000. Nobody in the case argued about the quality of the work or whether the money was owed. The entire dispute was the date.
Where a lien goes on a public job
On a regular private job, a lien goes on the property. Say you do $50,000 of electrical on a strip plaza reno, the GC pays you $30,000 and then stops, and your last day on site is March 1. By April 30, you register a lien on the plaza’s title for the $20,000 you’re owed, and the owner can’t sell or refinance clean until you’re dealt with.
You can’t put a lien on a city road, though. On public work like the Trillium Line, the claim goes against the holdback instead. For Bradley-Kelly, that 10% sitting in the chain was the only thing it could reach, and that’s exactly what the GC was trying to keep.
How long do you have to file a lien in Ontario?
In Ontario, you have 60 days from your last day supplying work or materials to preserve a lien. After that, you have another 90 days to perfect it, which means starting the lawsuit. Miss that window and the quality of your work doesn’t matter.
The clock starts on your last day of work. It doesn’t wait for your final invoice, and it doesn’t wait for the GC to tell you the job is closed. If you work outside Ontario, check your own province’s rules, because the deadlines differ.
Johny explained why 60 days is shorter than it sounds on a big project. Many commercial jobs only allow billing once a month, often between the 20th and the 25th. If your last day on site is October 1, you might not be allowed to bill until October 25. Then the payment certifier reviews the draw, which can take another 15 days or more. You’re 40 days past your last day before the amount is even approved, and the 30-day payment clock hasn’t started yet.
By the time the payment is late, your lien window has already closed. That leaves you deciding whether to lien a client before you know they won’t pay, and Johny pointed out that filing early usually lands badly with a client who says the money is coming. He thinks the system is broken. Either way, you have to plan around it.
Proving your last day on site
The whole case came down to when the work actually finished. Bradley-Kelly could show it was on site at Walkley Yard on January 25, and that’s what saved the $703,000.
If you can’t prove your last day with records, you’re arguing from memory against a GC’s lawyers. The records that hold up are the ones made at the time: dated daily logs, timestamped photos, delivery slips, texts or emails with the super.
Johny has been through this himself. He liened a developer who stopped paying for work that was already done, and the other side’s argument was that anyone can make up a timesheet. The answer that his lawyer called the smoking gun was GPS-pinned clock-ins showing when and where the crew started and finished each day, matched against payroll records. That claim was worth about $37,000. Paper timesheets wouldn’t have carried the same weight, because they’re easy to doctor.
His advice for any contractor, from one person in a truck to a big crew, is to set the process up from day one. Nobody buys car insurance after the accident.
Jobtable’s daily logs keep the date, your notes and your photos on every job, and you can send a log straight to your client in one click. Timesheets record where your crew clocked in and out. Both build the record you’d need long before anyone disputes it.
👉 Learn more at https://www.jobtable.com
Frequently asked questions
What is a holdback in construction?
A holdback is the 10% of each payment that a payer keeps back on a construction job. In Ontario, the Construction Act requires every payer in the chain to hold it, and it’s held in trust for the contractors and suppliers below them until the lien period runs out.
Does holdback apply to small jobs and renovations?
Yes. In Ontario there’s no minimum contract size. Holdback applies to any contract on a job where a lien could arise, including small commercial renos and residential renovations.
When is holdback released in Ontario?
On most jobs, the payer can keep the holdback until the 60-day lien period has expired, then has 14 days to pay it. For contracts signed after January 1, 2026, owners also have to release accrued holdback every year on the contract anniversary.
How long do you have to file a construction lien in Ontario?
You have 60 days from your last day supplying work or materials to preserve a lien, then 90 more days to perfect it by starting a court action.
Can you put a lien on a public road or city project?
You can’t register a lien on a public street. On that kind of public work, your claim goes against the holdback instead of the property, which is why the holdback mattered so much in this case.
This is general information about the law, not legal advice. Talk to a construction lawyer about your own job.
The GC in this case paid lawyers on the bet that a subcontractor couldn’t prove a date. Look at the jobs you have running right now. If someone made that same bet against you, would it pay off?